Construction of a new gas pipeline between Yangiyer and Akhangaran begins

Construction of a new gas pipeline between Yangiyer and Akhangaran begins Uztransgaz JSC continues to work within the framework of the "Program for Modernization and Improvement of the Efficiency of the Main Gas Transportation System of the Republic of Uzbekistan for 2021/2022."

FDI UzLITI Engineering LLC is in charge of the construction of a new gas pipeline. The customer is Transgazengineering LLC, the construction contractor is Nadymstroygazdobycha, and the subcontractor is Enter Engineering LLC.

The total length of the pipeline network under the project is 95 kilometers.To date, 1000 pipes with a diameter of 1220 mm have been delivered to the facility, totaling 12 km in length.

These works are being carried out by 22 engineers and other workers. The construction and installation work will be completed between October 2022 and March 2023.