Modernization is under go...

Modernization is under go... Uztransgaz JSC continues to work within the framework of the "Program for Modernization and Improvement of the Efficiency of the Main Gas Transportation System of the Republic of Uzbekistan for 2021/2022." In detail...

Pipelines are currently being laid on an 80-kilometer section of the Central Asia-Center gas pipeline's second line (CAC-II). The project involves approximately 90 workers and 100 pieces of equipment.

To date, 65 kilometers of pipeline with a diameter of 1220 mm have been welded. About 56 kilometers of these were laid in a trench.